Sunday, May 3, 2020
The Ceiling - Day Six
Today being Sunday, there will be no work today. Fortunately, there is very little work left on the ceiling. Monday, they should be finished with the molding. That will only leave the painting, which will be done by a different crew.
When contracted, the head installer estimated the work on the ceiling to take two weeks. It's taken far less time than that.
I'm not certain how long it will take the painters to finish, but the men putting down the floor tiles should begin Tuesday. They're estimating three days to lay the tiles. If all goes well, everything should be finished before next Sunday, and we can begin to put the house back to normal.
Labels:
Philippines,
Sibulan,
the house
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment